
![]() ![]() ![]() ![]() ![]() ![]() ![]() Work Progress on the PSP scheme ‘Nant de Drance’ The company Aare-Tessin A.G. for Electricity (Atel) together with the Swiss National Railway (SBB) are planning the development of the Pumped Storage scheme ‘Nant de Drance’, which is located between the existing reservoirs Emosson and Vieux Emosson in the Canton of Valais, Switzerland. The Emosson Reservoir, with an approximate capacity of 225 million m3, acts at present as the primary storage for the existing hydro-power stations of the Electricité d’Emosson S.A. and the SBB and will serve in the future pumped storage scheme as the lower reservoir. The Vieux Emosson Reservoir lies at an elevation 300 m above the Emosson reservoir and has an approximate capacity of 12 million m3. The new pumped storage station 'Nant de Drance', with an installed capacity of 600 MW, will require the construction of a 5.6 km long main access tunnel, a machine cavern, a transformer cavern and two parallel waterway systems, each comprising an intake and an out take, headrace and tail race tunnels, with vertical pressure shafts, which will be in part armoured with steel liners. The construction of access roads to the portal areas have been carried out in parallel. The replacement of the pipeline from the de-watering works to the neighbouring hydro-electric power station (SBB) has been started. Excavation to a depth of up to 14 m will be required. After test blasting, in which resulting vibration to neighbouring power stations was evaluated, the tunnel drive was started on 18. December 2008. The tunnel drive began for the above mentioned tunnel drives in double shifts. The break out of the 210 m dewatering gallery is expected towards the middle of February. The main construction work has been given to the consortium Marti/Implenia, and will start officially in January 2009 with the excavation and primary support of the portal area for the 5.6 km long main access tunnel. The tunnel has to be driven in the portal area only 3 meters under the existing railway line of the TMR in challenging geology, comprising unconsolidated colluvium and landslide material. Contemporaneously, the construction of the site village with accommodation and canteen facilities for up to 400 employees will be carried out. Patrick Furrer - Wasserkraftanlagen Nam Ngum 2 – A Lender’s Engineering Assignment Nam Ngum 2 is a 615 MW hydroelectric project being implemented in Lao PDR for energy export to Thailand. The project includes a 181 m high concrete faced rockfill dam, with a total volume of about 9.5 million m3; open chute spillway on the right abutment, fully underground power waterways in the left abutment; outdoor powerhouse equipped with three Francis units of 205 MW each under a design head of 154.5 m. The river diversion during construction is achieved through two concrete lined diversion tunnels of 11.7 m diameter and 1,150 m average length. With an average river runoff of about 200 m3/s, the project generates 2,218 GWh/y, all intended for export to Thailand.
The project company is owned by private and semi-private Thai companies, with an important participation from the Lao Government. The main shareholder is a Thai construction company, which is also the EPC Contractor for the construction of the project. Financing is provided by a group of Thai banks. Giuseppe Stevanella - Hydropower Plants AF-Colenco Ltd Awarded 1st Prize for a Geoscientific Computational Benchmark A team from AF-Colenco’s Department for Groundwater Protection and Waste Disposal participated in Couplex-Gaz, an international competition for the numerical modelling of two-phase (gas-water) flow and transport in porous media. ANDRA, the French National Agency for Radioactive Waste Management presented the nine participating teams with two test cases involving complex physical processes, extremely heterogeneous materials and different scales. Each team submitted its contribution in parts over a period of 2 years. The Scientific Committee evaluated the teams based on the solution approaches as well as computational efficiency, stability and accuracy. Jean Croisé - Groundwater Protection and Waste Disposal AF-Colenco Info November 2008 |















